The distribution network, the buried supply and return pipes between the plant and the houses, decides how much of the fuel reaches the radiators: for 400 m of trench with a 60 mm steel pipe at 80 °C supply and 50 °C return, the loss is 108 kW bare, 11.1 kW with 50 mm of wool-class insulation, and 72.5 kW if that insulation is wet. Choose a pipe that survives 80 °C, insulate and keep it dry, bury it, leave it room to expand, vent the high points, and pressure-test it at 1.5 times its working pressure before filling the trench.

What a village hot-water pipe network consists of, what each part contributes to loss or failure, and the build and commissioning sequence.

The Four Parts And What Each Decides

  1. Pipe — temperature rating and joints: Pipe Materials (Clay, Steel, Plastic).
  2. Insulation — the loss: Insulation Methods.
  3. Trench and burial — protection and frost: Burial Depth & Trenching.
  4. Expansion and venting — keeping the water and the pipe from damaging the system: Expansion & Venting.

The Heat Budget Of The Network

Reference: 400 m of trench with a 60 mm steel pipe, supply 80 °C and return 50 °C, ground 8 °C, 4,800 h season, 230 MWh delivered to 30 houses. From the full derivation in the insulation article:

CasePair loss, W per metre of trench400 m, kWSeason, MWhShare of 230 MWh
Bare steel270.5108519225%
50 mm wool-class insulation27.711.15323%
50 mm, wet (k = 0.5, assumed)181.372.5348151%

The same 400 m of pipe is therefore worth building or worthless depending on whether it is insulated and dry. Pumping cost is small by comparison; see Pump Requirements.

Build And Commissioning Sequence

  1. Survey the route and levels (Elevation Measurement); mark the high points for vents and the low points for drains.
  2. Dig the trench to the depth and width in the burial article, with a sand bed.
  3. Lay and join the pipe, with expansion allowances and an isolating valve at each branch.
  4. Pressure-test with water at 1.5 times working pressure before insulating. Salvaged Modern Pipe gives the 1.5-times rule for salvaged pipe, and Pressure Testing explains why to test with water and not steam. For a working pressure of 120 kPa (about 5 m of static head plus 72 kPa from the pump), test to 180 kPa.
  5. Insulate and case the pipe, sealing the ends and joints, then backfill in layers with sand around the pipe.
  6. Fill from the low point and vent the air from every high point.
  7. Heat in steps. Raise the temperature gradually, checking joints, expansion bends and supports at each stage, and watch the trench for steam or wet ground.
  8. Record the as-built route with distances to fixed landmarks; see Record Keeping.

Common Mistakes

  • Insulating before the pressure test. A leak under wet insulation is invisible.
  • Choosing the pipe by pressure rating alone. A plastic pipe rated for 20 °C is the wrong pipe at 80 °C.
  • No documentation of the route. Trench maps are the only way to find a leak.

Safety

Hot pressurised water in a trench

A pipe failure at 80 °C scalds anyone standing near the leak, and a pressure test with air or steam stores energy that a water test does not. Test with water only, keep people clear of the trench during the test, and shut and drain a section before it is opened.

What’s Next