Curing means keeping fresh cement damp so it can keep reacting and harden dense and watertight: keep a ferrocement tank wet for at least 14 days by covering it with wet burlap or plastic and spraying it twice a day, and cure each coat of cistern plaster for at least 7 days. Curing is not waiting for the mortar to dry; drying early is what cracks a tank, and rushed curing is the commonest reason one leaks.

Curing is the controlled keeping of newly placed cement mortar or concrete in a moist, protected state while it gains strength. For a water tank the aim is a dense wall with the fewest cracks, since cracks are leaks.

Cement Hardens By Reacting With Water, So Drying Out Stops It

Cement sets by a chemical reaction with water, not by drying. If the surface dries in sun or wind, the reaction stops at the surface and the mortar shrinks. A shrinking surface on a rigid wall cracks. The mortar then looks hard but is weak, porous and leaky.

The cisterns page gives the rule for ferrocement: keep the tank wet for at least 14 days, covered with wet burlap or plastic and sprayed with water twice daily, and states that rushed curing means a cracked tank. For the rendered lining of an underground cistern, each of the two coats is cured for at least 7 days and kept damp (Cement Plaster).

What You Need

  • Burlap, cloth sacking or old blankets — to hold moisture on the surface
  • Plastic sheeting — to hold the moisture in
  • A sprayer or a bucket and a soft brush — water must reach the surface without washing it away
  • Shade, from poles and cloth if there is none
  • A calendar, with the day each coat was placed

Method: Cover, Wet, Repeat

Step 1: Start early, gently. As soon as the surface is firm enough to take a wet cloth without marking, cover it. Before that, shade it from the sun.

Step 2: Cover the whole surface with wet burlap or plastic, inside and out where reachable.

Step 3: Spray twice daily, more often in hot or windy weather. The covering should never be seen dry and pale.

Step 4: Keep going for the full time. Count from the day of the last plastering.

Step 5: Do not fill the tank early. A tank filled before the cure is complete can crack under the load.

Worked Example

Calendar for a cistern lined in two coats, from day 0 when the first coat is placed:

  • Day 0: first coat placed
  • Days 0–7: kept damp (7 days)
  • Day 7: second coat placed
  • Days 7–14: kept damp (7 days)
  • Day 14: earliest the lining is ready to take water

Ferrocement runs on the same total of 14 days from the last plastering. If a heat wave or wind dries the cover during the cure, count the dry day as lost and extend the cure.

First-Fill Water

New cement leaches lime, so the first water in a new tank is alkaline and not good to drink. Fill it, let it stand, empty it, and repeat before putting it into use. Disinfect before drinking: chlorine at 50 mg/L for 24 hours is the dose used for a new well in Well Development; that is the dose added, not a residual.

Common Mistakes

  • Cure counted from the first coat, not the last. The final layer is the one at risk.
  • A cover that blows off. Weight the edges.
  • Spraying hard. It erodes a surface that has not hardened.
  • Letting the burlap dry between sprays. Dry burlap pulls moisture out.
  • Stripping props or forms early. A slab or shell is still weak.

Safety

Fresh cement burns and a damp cover can hide a hazard

Wet cement is alkaline and burns skin and eyes; wear gloves when handling it and when lifting wet cover. Do not climb into a covered, roofed or lidded tank to check the wall without ventilation and a rescue line: the air in a closed tank can be short of oxygen.