Make primary paths 2-3 m wide, wide enough for a cart or two people with loads to pass, and secondary paths to individual houses 1-1.5 m wide. Crown each path so rain drains to the sides, add a ditch where drainage is poor, and surface the primary paths with gravel, wood chips, flat stones or a raised boardwalk, because an unsurfaced path in a wet climate becomes a mud bog.

Path network design sets the width, grade, crown and surface of the foot and cart paths that join a settlement’s zones.

Width Follows The Biggest Thing That Must Pass

A primary path is sized by the widest normal traffic: a handcart, or two people each carrying a load, passing each other. That is the layout guide’s reason for 2-3 m. A secondary path serves one household and carries one person or a barrow, so 1-1.5 m is enough.

Surfaces trade labour against life:

SurfaceStrengthCost
GravelBest durability and drainageHauling and laying
Wood chipsComfortable underfootReplace about annually
Flat stones or salvaged paversPermanentLabour-intensive to lay
Raised boardwalkWorks in swampy groundTimber, and rot over time

What You Need

  • Gravel, chips, stone or timber for the surface, depending on the table
  • A line level or A-frame to check slope (A-Frame Level)
  • Spade and rake for crowning and ditches

Method: Crown, Drain, Surface

Step 1: Stake the centreline and set the finished level so the path never sits lower than the ground beside it.

Step 2: Crown the path. Make the centre slightly higher than the edges so rain runs off sideways. For roads, Road Layout gives a crown of 5-8%; a footpath needs less.

Step 3: Dig drainage ditches beside paths where the ground is poor. Run them to an outlet away from wells and houses (Drainage Ditches).

Step 4: Surface the primary paths from the table. Gravel is laid in layers over a dry, firm subgrade.

Worked Example: Surfacing A Primary Loop

Inputs: a primary path of 400 m, 2.5 m wide (mid-range of 2-3 m); gravel to the 175-275 mm combined thickness Gravel Roads gives for roads, used here as an upper bound for a path that carries carts.

  1. Area: 400 m × 2.5 m = 1,000 m².
  2. Volume at 0.175 m: 1,000 × 0.175 = 175 m³; at 0.275 m: 1,000 × 0.275 = 275 m³.
  3. A footpath of lighter use can take less, but a cart path should be built to the road thickness.

That is a large haul for a small settlement, which is why secondary paths are often left as compacted earth with a crown and a ditch, and gravel is spent on the primary loop.

Common Mistakes

  • No crown — water stands in the wheel ruts.
  • Wood chips on a steep path — they wash away; use stone steps or gravel.
  • Paths a metre too narrow for a stretcher.

Safety

Slippery and steep paths

A wet boardwalk or a steep chip-covered path causes falls, particularly with loads. Cut cleats or use stone on grades where people carry water, and keep path grade within what a loaded cart can hold: Road Layout limits loaded animal carts to about 8-10%.