Build a biogas digester in this order: choose a site close to the animals, downhill and at least 30 m from drinking water; size the plant from the daily feed and retention time; dig and build the body; waterproof and seal it; fit the inlet, outlet and gas outlet; then test it with water and with air pressure before loading. Every pit must have a lid or rail, and nobody enters a digester once it has held slurry.

Digester construction is the sequence of siting, sizing, building, sealing, fitting and testing a household biogas plant.

The Order Of Work

StageWhatPage
1Size from the feed and retention timeSizing the Digester
2Build the body (dome, drum pit or tube)Digester Types
3Make it watertight and gas-tightWaterproofing & Sealing
4Inlet and outletInlet & Outlet Design
5Stirring accessMixing & Agitation
6Gas holder, regulator and pipingGas Collection & Storage

Choosing The Site

  • Near the animals, so manure reaches the inlet without long hauling.
  • At least 30 m from drinking water and downhill of it, the distance the corpus gives for manure (Manure Management); digestate and leaks carry nutrients and pathogens.
  • Warm and sunny, because a warmer digester gives more gas (Temperature & Retention Time).
  • Away from the house and from any fire, with the gas pipe as short as practical.
  • Dry, stable ground with the water table below the pit floor, since a high water table floats and cracks an empty pit.

What You Need

  • Labour and a digging plan, with shoring for pits that are deeper than a person’s waist, and a second person above ground
  • Masonry, concrete or plastic, per the chosen type
  • Plaster and waterproofing materials
  • A means of testing: water, an air pump and a water-column gauge

Method: The Tests

Step 1: Water test. Fill the digester with water, mark the level on the wall, and recheck after 24 hours. A fall means a leak; find and repair it (Pond Lining and Waterproofing uses the same 24-hour check).

Step 2: Gas-tightness test. With the gas outlet connected to a water-column gauge, put air in to the working pressure, close the valve and watch the gauge for a day. Any fall is a leak. A structure that holds water can still leak gas (Waterproofing & Sealing).

Step 3: Seed and load with active culture.

Common Mistakes

  • Building before sizing.
  • No lid on the mixing pit or outlet tank.
  • Skipping the gas test because the water test passed.
  • Putting the digester above a well or spring.

Pits and confined spaces

A fresh or empty pit can hold carbon dioxide from decay or from nearby rotting matter, and a loaded one holds hydrogen sulfide and methane. Never go down alone, never rely on smell, and never go in to rescue someone; ventilate and use a line from outside (Safety Protocol, Manure Management). Shore every excavation against collapse.